July 14, 2005 - Day 7 of Remodel



Today the crews continued to dig out the side yard, piling up more and more dirt.


The ground needs to be dug deep, because the foundation for the retaining wall will need to be at least 2-3 feet below ground level.

It's good thing we got permits for all this. One of our neighbors called the city to complain. Fortunately for us, the city told them all the permits were in order, and everything was approved!