Wednesday, August 17, 2005

August 15, 2005 - Day 44 of Remodel


Today we moved out of our house for the remainder of the remodel.

Since the remodel requires installation of a new roof, and relocation of our only bathroom, moving out was a necessity.

Here are photos of our house -- empty.


















Click on any photo to see a larger view.

Sunday, August 14, 2005

August 12, 2005 - Day 42 of Remodel


The crews have put in the heating vents and the rough flooring.








The retaining wall concrete footing has also been poured. There is over four feet of concrete footing. The crew is now working on the
rebar framing for the actual retaining wall.


Click on any photo to see a larger view.

August 5, 2005 - Day 35 of Remodel


The crews have put in the rough plumbing.

You can see the pipes for the external hose bibs, and the master bedroom shower and sinks, as well as the sewer lines for the master bedroom sinks and toilets.












There is also a nice photo of a bird my Dad took.